Project Milestone | Description (Days from Appointed Date) | Planned | Actual | Delay (No. of months) | Current Status | ||
---|---|---|---|---|---|---|---|
Physical Progress (%) | Scheduled Date | Physical Progress (%) | Achieved Date | ||||
Project Milestone-I | 150th day | 20% | 28-03-2024 | 20% | 14-02-2024 | ||
Project Milestone-II | 330th day | 35% | 24-09-2024 | 35% | 30-04-2024 | ||
Project Milestone-III | 510th day | 75% | 23-03-2025 | ||||
Schedule Completion | 730th day | 100% | 29-10-2025 |