S. No.ItemDescription
1Project NameConstruction of 4-Lane green field highway from km. 35.00 to 49.155
of NH -731A with paved shoulder on Hybrid Annuity Mode in
the state of Uttar Pradesh.
2NH No. (Old / New)New NH -731A
3Mode of the ExecutionHybrid Annuity Mode (HAM)
4No. of Lanes/ Configuration4 Lane
5Length of the Project (in Km)14.155 Km
6No. of Major Bridges1 Nos
7No. of Fly Over2 No.
8No. of VUP6 No.
9No. of Minor Bridges10 No.
10No. of ROB1 No.
11No. of Culvert26 No.
12Concessionaire NameRam Van Gaman Path Private Limited.
13EPC ContractorS&P Infrastructure Developers Pvt. Ltd and Sunny Infraproject Pvt. Ltd.
14Date of Award (LOA Date)17 January 2023
15Appointed Date30 October 2023
16Construction Period (in Days)730 Days
17Authority NameMinistry of Road Transport and Highways, NH PWD-Prayagraj, Uttar Pradesh
18Independent EngineerM/S L N Malviya Infra Project Private Limited.
19Safety ConsultantS.E.S. (Specialized Engineering Services Pvt Ltd)